Transmission Line Project

The Chimney Canyon Solar and Transmission Line Project aims to enhance grid reliability across Navajo County and Arizona by interconnecting a proposed solar generating facility to key transmission infrastructure.

Transmission Line Project Characteristics

Up to two routes to be developed

Routes are anticipated to be up to10 miles in length with a right-of-way of at least 150 feet

Pole structures are anticipated to be monopole design, up to 200-ft in height, and spaced approximately 800 - 1,000-feet apart

Multiple potential transmission routes are under analysis

Project Timeline

  • Certificate of Environmental Compatibility application filed in October 2025.
  • Arizona Transmission Line Siting Committee Public Hearing completed December 15 – 17, 2025.
  • Construction anticipated to begin as early as Q1 2027.

Get in Touch

The Clearway team wants to hear from you. Please fill out this form or email chimneycanyonsolar@clearwayenergy.com to get in touch.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.